The Missouri Department of Transportation (MoDOT) is planning to remove and replace the Providence Road bridge over Interstate 70 as part of its Improve I-70 program. Construction is currently anticipated to begin in late May and last for 5 months so spread the word to friends, customers, and colleagues about the best ways to navigate around the closure.
From 9 p.m. on May 29 to 9 a.m. on May 31, construction crews working with MoDOT plan to demolish and remove the Providence Road overpass bridge and the pedestrian bridge.
Traffic on I-70 and Providence Road will be impacted as follows:
On I70:
On Rangeline:
On Providence:
Once the demolition and cleanup are complete on Sunday morning, May 31, I-70 will return to normal traffic patterns.
As the new bridge is built over a five-month period, there will be several traffic impacts to Providence Road:
Construction of the new overpass bridge is expected to continue through the end of October. All work is weather-permitting and subject to change.
The new overpass bridge will be longer to accommodate the new I-70 lanes underneath and will be raised to allow taller vehicles to pass under it.
The overpass will feature pedestrian crossings on both sides and will have added beautification elements including decorative lighting, enhanced railings and fencing, stone-pattern retaining walls, and bridge facade elements. These beautification improvements are funded, in part, by the Business Loop CID to create a gateway onto The Loop we can be proud of.